Light up Louisiana

This project includes necessary utility, drainage and pedestrian improvements and will also include upgrades to paving, landscape and lighting along Louisiana Street in two separate stretches.


Louisiana Street between:

  • Church Street and Kentucky Street
  • Tennessee Street and S.H. 5


Current Project - Louisiana West

Click on image for larger map

Light up Louisiana Construction Map

View of road, one side under construction

View of road with sidewalk under construction

ProgressProject Phase / Step
Green dot with check mark - Phase / Step completed successfullyPhase 1 – waterline installation at Louisiana and Church
Green dot with check mark - Phase / Step completed successfullyPhase 2 – southern half of roadway
Green dot with check mark - Phase / Step completed successfully
  • Demolition
Green dot with check mark - Phase / Step completed successfully
  • Utility installation
Green dot with check mark - Phase / Step completed successfully
  • Subgrade Prep/Street Paving
Green dot with check mark - Phase / Step completed successfully
  • Sidewalk
GreenDot - Project in ProgressPhase 3 – northern half of roadway
Green dot with check mark - Phase / Step completed successfully
  • Demolition
Green dot with check mark - Phase / Step completed successfully
  • Utility installation
Green dot with check mark - Phase / Step completed successfully
  • Subgrade Prep/Street Paving
GreenDot - Project in Progress
  • Sidewalk
GreenDot - Project in ProgressPhase 4 - Final cleanup items
GreenDot - Project in Progress Indicates the particular project phase / step is in progress.

Top

Coffee with the Contractor: Bi-Weekly Meetings

Have your questions answered directly by the contractor, Axis Contracting, Inc., and learn about the upcoming schedule.

When: Friday, October 2

Time: 9:30 a.m.

Where: MPAC Lawn, west side picnic tables


Check on the status of this project at McKinneyTexas.org/ProjectStatus.

Questions? Send us an email at Louisiana@McKinneyTexas.org.


Top

Traffic Status

A lane on the northern half of the roadway remains closed through the project limits. Traffic has been placed on the newly constructed southern traffic lane. One lane of travel will remain open for eastbound traffic on Louisiana Street throughout construction.


All travel lanes and parking are expected to be open for vehicle traffic during the first week of October. Intermittent temporary lane closures on either side of the roadway are expected throughout the month of October as needed to complete all remaining items.